Project Description:

This project involved replacing 162 curved glass panels at levels 0 - 4 and 360 curved and flat panels at the top of the global headquarters via a unique and specially designed access platform. Whilst replacing the glazing at 200 metres above the ground, a new day / night signage solution was also being installed.

This project was particularly challenging because the works were taking place in a live building with over 9,000 occupants that is occupied 24/7.